Construction Schedule: Eight weeks
Project: West Moors Fuel Depot
Services: Electrical, Design
Client: Mildren Construction
Contract Value: £70k
Design and install of a new CompEx installation at West Moors Petroleum Depot. This involved the installation of various switchgear, cabling and controls including and intrinsically safe system for the operation of fuel gauges and mains electrical supplies to operate fuel valves.
We were involved in this project from the start, consulting with the main contractor and the client to implement the various systems through to the commissioning at project completion.